Project Milestones Status

Project Milestones

Project Milestone Description (Days from Appointed Date)-CA Description (Days from Appointed Date)-EOT
Planned
Actual (Month)
Remarks
Financial Progress (%) Scheduled
Date
Revised Scheduled
Date as per EOT
Financial Progress (%) Revised Date
Milestone I 180 180 20% 29th Jun 2019 20.03 % 30th Aug 2019 Achieved (Within 90 days period stipulated in Clause 12.3 of CA)
Milestone II 360 360 35% 26th Dec 2019 35.18 % 02nd Jan 2020 Achieved (Within 90 days period stipulated in Clause 12.3 of CA)
Milestone III 540 630 75% 23rd Jun 2020 23rd Sep 2020 75.93% 20th Mar 2021 Achieved (Within 90 Days Grace Period of 2nd EOT)
Schedule Completion Date 730 910 100% 30th Dec 2020 28th Jun 2021   PC issued on 28.06.2021.