Project Milestones
Project Milestone | Description (Days from Appointed Date)-CA | Description (Days from Appointed Date)-EOT |
Planned
|
Actual (Month)
|
Remarks | |||
---|---|---|---|---|---|---|---|---|
Financial Progress (%) | Scheduled Date |
Revised Scheduled Date as per EOT |
Financial Progress (%) | Revised Date | ||||
Milestone I | 180 | 180 | 20% | 29th Jun 2019 | – | 20.03 % | 30th Aug 2019 | Achieved (Within 90 days period stipulated in Clause 12.3 of CA) |
Milestone II | 360 | 360 | 35% | 26th Dec 2019 | – | 35.18 % | 02nd Jan 2020 | Achieved (Within 90 days period stipulated in Clause 12.3 of CA) |
Milestone III | 540 | 630 | 75% | 23rd Jun 2020 | 23rd Sep 2020 | 75.93% | 20th Mar 2021 | Achieved (Within 90 Days Grace Period of 2nd EOT) |
Schedule Completion Date | 730 | 910 | 100% | 30th Dec 2020 | 28th Jun 2021 | PC issued on 28.06.2021. |