Salient Features
Project Name | Four Lanning of Sangli – Solapur (Package – III: Watambare to Mangalwedha) Section of NH – 166 from existing Ch. Km 272.394 to Ch. Km 314.969 (Design Ch. Km 276.000 to Ch. Km 321.600) of length 45.600 Km in the State of Maharashtra on Hybrid Annuity |
---|---|
NH No. (New/ Old) | 166 |
Mode of the Execution | Hybrid Annuity Mode |
No. of Lanes/ Configuration | Four Lane with Paved Shoulder |
Length of the Project (in Km) | 45.6 Km. |
Total Project Cost (in Cr) | INR 957 Cr. |
Banker Name | HDFC Bank |
Bypass | 2 Nos (Sangola Bypass- 12.070 kms) and (Andhalgaon Bypass- 0.910 kms) |
No. of Bridges | Major Bridges -02 Nos Minor Bridges- 11 Nos |
No. Of Culverts | Hume Pipe Culverts – 64 Nos Box Culvert – 06 Nos |
No. of Under Passes | (VUP/LVUP)- 19 Nos |
No. of ROB | 01 Nos |
Concessionaire Name | M/s GR Sangli Solapur Highway Pvt Ltd (GSSHPL) |
Date of Award (LOA Date) | 27th March 2018 |
Agreement Signing Date | 20th June 2018 |
Appointed Date | 31st December 2018 |
Concession Period | 17 Years |
Construction Period (in Days) | 730 Days + 180 Days = 910 Days |
EOT (Approved) | 180 Days |
O&M Period (in Years) | 15 Years |
Scheduled Date of Completion | 30th December 2020 |
Revised Scheduled Date of Completion | 28th June 2021 as per (90 Days + 90 Days EOT) |
Provisional Certificate Date (is if any) | w.e.f 28.06.21 for 34.360 Km (BHS) |
Independent Engineer | Dhruv Consultancy Services Ltd. (In association with Acculead Consultancy Services LLP) |
IE Agreement Date | 24th May 2019 |
IE Mobilization Date | 07th June 2019 |